PO-10320 | Nova Industrial

Buyer: Ali Noor

PO Summary

PO Date
2026-04-20
Incoterms
FOB
Total Value
USD 185,400
Delivery Location
Jebel Ali, Dubai
Payment Terms
30% Advance, 70% Before Shipment
Delay (Days)
2
PO Attachment
PO-10320.pdf

PO Status

1
PO Issued
20 Apr 2026
2
Follow-up Started
22 Apr 2026
3
Supplier Response
25 Apr 2026
4
Ready Date Updated
28 Apr 2026
5
Ready Date Confirmed
04 May 2026
6
Items Confirmed
05 May 2026
7
Logistics Planned
06 May 2026
8
Submitted to Logistics
07 May 2026
9
Booking Confirmed
09 May 2026

Item Table

SelectItem CodeDescriptionOrdered QtyConfirmed QtyPartial FlagReady DateDelay (Days)StatusLogistics StatusContainer Booking RefRemarkReminder
IT-0091Steel Sheets 4mm1000No0Not SubmittedBK-2402
IT-0112Copper Wire Roll500No1Not SubmittedBK-2402
IT-0145Galvanized Bolts2500Yes3Not Submitted-

Follow-up Timeline

2026-04-20 PO Sent | System | PO released to supplier
2026-04-22 Reminder Sent | Ali Noor | Email reminder #1
2026-04-25 Reminder Sent | Ali Noor | Reminder #2 and call
2026-05-04 Supplier Response | Nova Industrial | Ready date confirmed by email

Logistics

Book New Container
PO Number Booking Ref # Vendor Name Customer Name Port Of Discharge Ship Via Cut Off Date Fulfillment Status Status Actions
PO-10320 BK-2402, BK-2399 Nova Industrial GEMCO Trading LLC Jebel Ali Sea 2026-05-10 Full Saved
PO-10328 BK-2403 Nova Industrial GEMCO Trading LLC Jebel Ali Sea 2026-05-11 Partial Submitted

Activities

Planned DateOwnerPlanned ActionStatusAction
2026-05-12 10:30 Ali Noor Follow-up call with supplier for balance quantity Pending
2026-05-14 15:00 Ali Noor Send reminder for second shipment ETD confirmation Pending
Date & TimeUserActionDetails
2026-05-05 10:15Ali NoorPO OpenedOpened PO detail page
2026-05-05 10:18Ali NoorStatus ChangedPO status updated to Ready for Logistics
2026-05-05 10:21Ali NoorReminder SentFollow-up reminder sent to supplier by email
2026-05-05 10:24Ali NoorReady Date UpdatedShipment type set to Full Shipment with ready date 2026-05-08
2026-05-05 10:28Ali NoorPartial Plan AddedSplit plan added for IT-0145 (1800 on 2026-05-10, balance next lot)
2026-05-05 10:31Ali NoorReady Date ConfirmedSupplier confirmed by Email with attachment proof
2026-05-05 10:35Ali NoorItem UpdatedIT-0145 qty/date/status/remark updated inline
2026-05-05 10:39Ali NoorItem Reminder SentReminder sent for item IT-0112 from item table
2026-05-05 10:43Ali NoorPO Attachment ViewedPO-10320.pdf opened in embedded preview
2026-05-05 10:46Ali NoorPO Attachment DownloadedPO-10320.pdf downloaded
2026-05-05 10:50Ali NoorLogistics SubmittedPreferred ETD, POL, container type and priority submitted
2026-05-05 10:54Ali NoorRecord SavedAll PO detail changes saved